can 1 1/4"rock go through 3"hose
SUPERDOFFER 12-11-2009
comment profile send pm notify

I was always learned it can not, but today we took the chance and proved it can.

biged 12-11-2009
reply profile send pm notify

What did you do flood it with water, you must like cleaning hose.

mtnpumper 12-11-2009
reply profile send pm notify

What was the %, was it 1 1/4 - ? That's impressive it either will or won't! Seems to be the design at the end.

SUPERDOFFER 12-11-2009
reply profile send pm notify

It was 50% big rock and 50% pea gravel and very high in the cement 5 inch slump, and as bonnus somme fly as. c28/35 xf4 Whe did a parking dek with pea gravel. and for a inclined plane there was an other mix. so whe had the choice, chaince hose or give it a try.


putzman1975 12-11-2009
reply profile send pm notify

i done that before trick is dont drown it with water pump it tight about 4 inch slump worked for me

mtnpumper 12-11-2009
reply profile send pm notify

50 50 1 1/4 and sand, wow!

Telealbelt 12-12-2009
reply profile send pm notify

Everybodys stone pile is different.  I've had 1 1/4 mix that is so stoney the S tube won't move.

nzpump 12-12-2009
reply profile send pm notify

Hey Superdoffer you would only use river pebble where you are not crushed aggregate isnt it ?

SUPERDOFFER 12-12-2009
reply profile send pm notify

mainly river peble, some crushed rocks for the finnes. but whe have also mixes whit a pers. reciceld concrete. 

SUPERDOFFER 06-13-2010
reply profile send pm notify

Hey dipstick 4"hose isn't havy if you know howe to handel it. I think  you mis the men in red, and the G boys. L.O.L. They are the only one's who can handel 60 cubic meter an hour whitout soaking it whit water.


SUPERDOFFER 06-15-2010
reply profile send pm notify

http://video.concretepumping.com/video/442/50-meter-system