The Cat | 10-11-2008 | comment profile send pm notify |
|
||
baddassduramax | 10-11-2008 | reply profile send pm notify |
looks like a pretty tedious job! did it take a while? |
||
pink panther | 10-11-2008 | reply profile send pm notify |
Those are pretty good pics cat. What size pump is that? |
||
The Cat | 10-11-2008 | reply profile send pm notify |
hi guy's..it's was a new bridge been put in from st ives to cambridge for the new bus link...we were stitching the precast section togeather..there was me on my putz 63 and mick on his put 47/5 we both had to move reach what we had to do...i think the whole bridge meaure's about 450 meter's long.. the job it self would'nt of took very long only for the fact we had to wait for the concrete whitch was only 1 minute away ... i could of shout'd for my next load the plant was that near.. |