bulldog13118 | 05-25-2010 | comment profile send pm notify |
has anyone pumped straight down a mine shaft using 1000 feet of hard line, then a 90, then 800 feet of line? |
||
Joe R | 05-25-2010 | reply profile send pm notify |
This type of system is standard practice for paste back fill or stabilization of the site. Our Ultra 600 abrasion resistant pipe is a perfect fit for this. Please give me a call and we can discuss this further. 262-284-7812 Joe Ultra Tech Pipe/ Construction Forms |
||
zuat150 | 05-25-2010 | reply profile send pm notify |
pumped down 350 ft then 100 ft out its fine till you stop then there is this awful suction going on and after cleaning out around the rockvalve twice i realized you must pump the hopper all the way down if you must stop oh and we filled the line with water to the 90 to catch the grout |
||
Dipstick | 05-27-2010 | reply profile send pm notify |
No. But I sure would like to be there when you're gona do that!!! |
||
pump wrench | 05-31-2010 | reply profile send pm notify |
yes i have several times 1000 t0 1400 feet down and then went 1200 to 2500 feet out. call me i will give you some pointers. 813-334-5552 |